In “full face” method of constructing tunnels, the first operation relates to

  • ARemoval of bottom portion
  • BExcavation of one drift in the centre
  • CRemoval of top portion
  • DExcavation being done along the periphery
Correct Answer : (D)

Excavation being done along the periphery