Q.

In hydroelectric power plants

  • AOperating cost is low and initial cost is high
  • BOperating cost is high and initial cost is low
  • CBoth Operating cost as well initial cost are high
  • DBoth Operating cost as well as initial cost are low
Correct Answer : (A)

Operating cost is low and initial cost is high

Hints :

In hydroelectric power plants Operating cost is low and initial cost is high.